2 Assign a task
Those who do the writing, translating or reviewing must be assigned to an article by the master manager, even if it is themselves.
Task assignment is usually what is done for an article after its initial creation or cloning and following setup, or when required for updating it.
- a.
Locale to be affected. Always the master if no other locales. - b.
Phase as the type of task being assigned. - c.
User ID of the person the task is being assigned to. If only one, they are automatically selected. - d.
Review types – at least one required. Only shown for a review. - e.
Due as a duration from the current day. Default is 4 weeks. - f.
Note – optional instructions for the assignee.
If time is not critical,
- a.At the end of the edit navigation bar for the Article head, History and Article body pages.
- b.On the article's row in the In progress section of the
Work list page.
Steps
△☰ Indicates the step has learning notes. Click its checkbox to show them.
The role to perform this procedure is: Master manager.
- a.Clicking on the
History orUpdate buttons in theVersions row of the Details section of theArticle head page for a newly created or cloned article. - b.Clicking on the
Phase column for the article in the In progress section of theWork list page. - c.If in the
History page with no phases, clicking on theUpdate button in the row for the latest release.
by clicking the
The available phases are listed, along with a
See Editing phases for phase details and some typical sequences.
If there is only one phase, the next step will be automatically done.
by clicking the
The master manager will be the first user listed and will be selected. The 4 weeks
by clicking the radio button for each parameter, and check the required review types if required.
by clicking the
by clicking the
- a.If for self, the available phase is
Query , and the task can be commenced by clicking theLatest button to show the Article body page for the article. - b.If for a contributor (has a _ at the end of their ID), the ending task (such as
Written when assignedWrite ) will be automatically generated, allowing further tasks to be assigned immediately. - c.Otherwise, the available phases are
On hold andNote , and an email is sent to the assignee advising them of the request.